Weber Genesis Silver B Gas Grill Gas Grill User Manual


 
16
Figure 3
Figure 5
Figure 4
25
5/8
1
2
3
4
Step 5
Measure and drill holes
You will need: Completed frame assembly, base
panel, tape measure, and pencil.
ƽCAUTION: Combustible materials should never
be within 24 inches of the top, bottom, back or
sides of the barbecue. Do not locate under
overhead combustible construction.
Note - With the lid open the depth of the barbecue
is 28 inches, front to back.
Set the completed frame assembly in position on your
deck, concrete pad, or patio for anchoring. Measure the
distance from the outside of the base plate to the
outside of the other base plate. It should be 26 5/8”
across. Figure 3.
Note: If the measurement is not 26 5/8” across
adjust the legs as necessary so that the
measurement is 26 5/8”.
Place the base panel in between the legs to insure fit.
Figure 4. Once the fit is established, remove the base
panel and mark the holes.
ƽCAUTION: A minimum of 2 bolts are required on
each side.
You are now ready to anchor the base.
Step 6
Typical installation of the base for an existing
concrete patio, new pad or wood deck
ƽCAUTION: Combustible materials should never
be within 24 inches of the top, bottom, back or
sides of the barbecue. Do not locate under
overhead combustible construction.
Note - With the lid open the depth of the barbecue
is 28 inches, front to back.
For anchoring, we recommend use of one of the
following methods:
ƽWARNING: Whichever method used, the base
must be bolted down (anchored) at a minimum of
four anchoring points (two per side) prior to
barbecue assembly. One anchor in each corner of
the base plate. Figure 5.