FRAMING
Construct framing using dimensions shown if
Figures 6, 7 and 8. (Use the gure applicable to
your application.) Figure 6 shows the framing
dimensions prior to having the appliance in place.
If installing on a platform, platform must be solid,
at and fully supported (see Figure 7). Once the unit
has been tted, bring studs in against nailing anges
located on the side of the appliance making sure
a 1" clearance is maintained as shown in Figure 8.
If the replace is to be installed directly on carpeting,
tile (other than ceramic) or any combustible mate-
rial other than wood ooring the replace must be
installed upon a metal or wood panel extending the
full width and depth of the replace.
Figure 6 - Framing Dimensions Prior to
Placing Appliance
Figure 8 - Securing Appliance with
Nailing Flanges
52
3
/
4
"
Min.
41"
25
5
/
8
"
VENT PIPE INSTALLATION
A 6" B-1 type gas vent pipe is a double wall, vent-
ing system (not supplied) which must be installed
during rough framing of the appliance. Any B-1
type gas vent system may be used for proper vent-
ing as long as the vent system is installed per the
vent manufacturer’s recommendations.
DESA supplies this appliance with a tapered starter
pipe for a snug t. Slide B-1 type vent pipe over
this starter pipe until vent pipe is fully seated.
Secure this rst section of B-vent pipe by strap-
ping the connector around the vent pipe and then
tightening the strap with any 1/8" nut and bolt (see
Figure 9). Note: Visually inspect for proper vent
connection by looking inside top of appliance. If
connection does not appear to be correct, contact
your local service technician.
Figure 9 - Installing B-Vent Pipe
Nailing
Flange
1" Min. to
Combustibles
Prepared
Framing
Nails or
Screws
B-1 Type
Vent (Not
Supplied)
Strap
(Fasten with
1/8" Screw
or Bolt)
52
3
/
4
"
Min.
24"
*
Figure 7 - Framing Dimensions Prior to
Placing Appliance Using a Platform
*As required by design as
long as ceiling clearance is
maintained