FIREPLACE INSTALLATION

1. Frame opening for replace using dimen-
sions shown in Figures 4 and 5.
2. If replace is to be installed directly on
carpeting, tile (other than ceramic) or any
combustible material other than wood
ooring, replace must be installed upon
a metal or wood panel extending full width
and depth of replace.
3. Set replace directly in front of this open-
ing and slide unit back until nailing anges
touch side framing.
4. Check level of the replace and shim with
sheet metal if necessary.
5. Before securing fireplace to prepared
framing, ember protector (provided) must
be placed between hearth extension (not
supplied) and under bottom front edge of
replace to protect against glowing embers
falling through. If replace is to be installed
on a raised platform, a Z-type ember pro-
tector (not supplied) must be fabricated to
t your required platform height. Ember
protector should extend under replace a
minimum of 1
1
/
2
". Ember protector should
be made of galvanized sheet metal (28
gauge minimum to prevent corrosion.
6. Using screws or nails, secure replace to
framing through anges located on sides
of replace.
30.125"
59" (50" Models)
58.125"
67.125"
51.25" (42" Models)
45.25" (36" Models)
28.250" (36" Models)
Figure 4 - Framing Dimensions
71" (50" Models)
100" (50" Models)
65" (42" Models)
92" (42" Models)
86.5" (36" Models)
61" (36" Models)
Maintain 1
1
/2"
Clearance
at Sides and
Back of Fireplace
1
1
/2" Clearance
Not Required at
Nailing Flanges
Figure 5 - Corner Installation

To determine the safest and most efcient
location for the replace, you must take into
consideration the following guidelines:
1. The location must allow for proper clear-
ances (see Figures 4 and 5).
2. Consider a location where replace will
not be affected by drafts, air conditioning
ducts, windows or doors.
3. A location that avoids cutting of joists or
roof rafters will make installation easier.
4. An outside air kit is available with this
replace (see Optional Outside Air Kit on
page 8).


Back and sides of replace 1
1
/
2
" min.*
Front of replace 48" min.
Floor** 0" min.
Perpendicular wall to opening 18" min.
36" Models 12" min.
Top spacers 0" min.
Mantel clearances
see Mantels, page 7
Chimney outer pipe surface 2" min.
36" Model 1" min.
* Not required at nailing anges
** See step 2 of Framing
-
quired air spaces with insulation
or other materials.

Residential Installation
Minimum height of chimney, measured from
base of replace to ue gas outlet of termina-
tion, is 16 feet for straight ue or a ue with
one elbow set. Maximum distance between
elbows is 6 feet. For systems with two elbow
sets, minimum height is 22 feet. Maximum
height of any system is 50 feet. This measure-
ment includes replace, chimney sections and
height of termination assembly at level of the
ue gas outlet (see Figure 15, page 11).

Outdoor Installation
Minimum height of chimney, measured
from base of replace to ue gas outlet of
termination, is 9.5 feet (minimum of 4 feet of
chimney pipe sections required for outdoor